Mississippi Lien Provision Assistance Guide

The Credit Management Association Lien Provision Assistance Guide provides provisions to meet individual state statutes in all fifty states. CMA makes no warranty expressed or implied in respect to the information provided on this site. The information contained is not to be construed as legal advice. For more detailed information, we encourage you to review the statutes regarding lien provisions specific to the state you are providing materials or improving property. For legal information, CMA suggests you consult with an attorney.

PRIVATE

PUBLIC
Obtain Copy of Payment Bond
FEDERAL
Obtain Copy of Payment Bond
Preliminary Notice Commercial/multi-dwelling residental within 30 days of first furnishing; residential single family dwelling 10 days prior to recording a lien Recommended but not required for most projects Recommended but not required
Lien 90 days from last furnishing N/A N/A
Bond Claim 90 days from last furnishing 90 days from last furnishing 90 days from last furnishing
Release Upon satisfaction Upon satisfaction Upon satisfaction
Suit 180 days from lien recording or 90 days from notice of contest 1 year 1 year

 