The Credit Management Association Lien Provision Assistance Guide provides provisions to meet individual state statutes in all fifty states. CMA makes no warranty expressed or implied in respect to the information provided on this site. The information contained is not to be construed as legal advice. For more detailed information, we encourage you to review the statutes regarding lien provisions specific to the state you are providing materials or improving property. For legal information, CMA suggests you consult with an attorney.

PRIVATE PUBLIC
Obtain Copy of Payment Bond
FEDERAL
Obtain Copy of Payment Bond
Preliminary Notice Optional: as soon as possible or within lien recording period Recommended but not required Recommended but not required
Notice of Intent 10 days prior to recording lien N/A N/A
Bond Claim N/A 90 days from last furnishing 90 days from last furnishing
Lien 4 months from last furnishing (laborers: record lien after last furnishing labor or within 2 months from job completion) N/A N/A
Release 10 days after satisfaction Upon satisfaction Upon satisfaction
Suit 6 months from last furnishing or completion 6 months 1 year

 